When one of our valued clients come to us with a challenge, we were to assist. As this Monopile manufacturer experienced a lack of storage on their yard they were looking for more space. However this additional space was across the water, meaning the Monopiles needed to be transported over water. That is where we came in.
Our trained and experienced SPMT crew are performing RoRo operations to transport the newly fabricated monopiles to the additional storage yard. Their monopile, with a length of 84 meters and a weight of 1,160 tons, was transported using a 2 x 24 axle lines SPMT configuration with the in-house designed Q3 foldable transport saddles. More monopiles to be transported are yet to come.
Moving barge SL8 underneath JUB Apollo
Q3 Heavy Lift proudly supported Mammoet-Giant with a unique and complex operation in the Port of Kaohsiung, Taiwan. π As barge master, we played a key role in maneuvering the barge SL8 underneath the Jack-Up Barge Apolloβa task that required both precision and close...